Paratext

  • Registration
  • Downloads
  • Support
  • Features
  • News
Home » FAQs » What if a task can or needs to be worked on in more than one stage?

January 22, 2020 By Doug Higby

What if a task can or needs to be worked on in more than one stage?

Adjust the “When can this task start?” setting to include all stages where the task can be worked on.

In the example above, the drafting of the back translation must be completed in stage three.  If I want to allow the team to work on the back translation in any of the earlier stages, then I change the “When can this task start?” setting to “Any time.”

Was this helpful?

Let us know if you liked the post. That’s the only way we can improve.

Quick Support Links

  • Paratext FAQ
  • Paratext Training Videos
  • Scripture Markup (USFM)
  • Paratext Training Plans
  • Paratext Supporter Forum

Upcoming Events

  1. Tracking and Analyzing Biblical Terms in Paratext – Session 1 of 4

    April 19 @ 10:00 am - 11:30 am EDT
  2. Tracking and Analyzing Biblical Terms in Paratext – Session 2 of 4

    April 20 @ 10:00 am - 11:30 am EDT
  3. Tracking and Analyzing Biblical Terms in Paratext – Session 3 of 4

    April 21 @ 10:00 am - 11:30 am EDT
  4. Tracking and Analyzing Biblical Terms in Paratext – Session 4 of 4

    April 22 @ 10:00 am - 11:30 am EDT

View All Events

News and Updates

  • Keyboard Shortcuts Are Here to Help You! April 7, 2021
  • Making a Glossary in Paratext March 16, 2021
  • Collaboration through Project Sharing February 15, 2021
  • New Tool for Printing from Paratext January 11, 2021
  • Paratext 9.1 has now been released! December 17, 2020

Privacy/Terms

  • Paratext Terms of Use
  • Privacy Policy

Development Partners

  • United Bible Societies
  • SIL International

Supporting Tools

  • Paratext Registry
  • Publishing Assistant
  • The Digital Bible Library

Copyright © 2016, United Bible Societies & SIL International, All Rights Reserved.