What if a task can or needs to be worked on in more than one stage?

Adjust the “When can this task start?” setting to include all stages where the task can be worked on.

In the example above, the drafting of the back translation must be completed in stage three.  If I want to allow the team to work on the back translation in any of the earlier stages, then I change the “When can this task start?” setting to “Any time.”

Was this helpful?

Let us know if you liked the post. That’s the only way we can improve.

Quick Support Links

  • Paratext FAQ
  • Paratext Training Videos
  • Scripture Markup (USFM)
  • Paratext Training Plans
  • Paratext Supporter Forum

Upcoming Events

There are no upcoming events at this time.

News and Updates

  • New Tool for Printing from Paratext January 11, 2021
  • Paratext 9.1 has now been released! December 17, 2020
  • Expand your Team with Paratext Lite October 28, 2020
  • Paratext 9.1 Beta is Now Available August 25, 2020
  • Enhanced Resource Superpowers June 5, 2020

Privacy/Terms

  • Paratext Terms of Use
  • Privacy Policy

Development Partners

  • United Bible Societies
  • SIL International

Supporting Tools

  • Paratext Registry
  • Publishing Assistant
  • The Digital Bible Library

Copyright © 2016, United Bible Societies & SIL International, All Rights Reserved.